File #: ID#15-2198    Version: 1 Name:
Type: Discussion and Recommendation Status: Consent Agenda
File created: 3/5/2015 In control: Board of Public Works
On agenda: 4/9/2015 Final action: 4/9/2015
Title: Approve Contract Change Order No. 1 with Ray Stadler Construction for Les Paul Performance Center Remodel. The change order decreased the Contract by $10,900.00 for a new contract total of $181,958.00
Attachments: 1. change order No 1 for Ray Stadler Les Paul Remodel