ID#18-0567 1A. MinutesApprove Minutes of April 5, 2018.approvedPass Action details Video Video
ID#18-0568 1A. BondsApproval of BondsapprovedPass Action details Video Video
ID#18-0571 1A. PaymentsApproval of PaymentsapprovedPass Action details Video Video
ID#18-0574 1A. ResolutionResolution for preparing plans and specifications and to advertise for bids for the construction of the W. Sunset Drive Pavement Patching and Diamond Grinding project.recommended for Council ConsentPass Action details Video Video
ID#18-0609 1B. ResolutionResolution Opposing the Closing or Blocking of MacArthur Road to Accommodate Railroad Activities. recommended for Council ConsentPass Action details Video Video
ID#18-0575 1A. Bid/RFPBids Received: Friday, April 13, 2018, at 11:00 A.M. Resurfacing of Asphalt Streets - 2018 The Board of Public Works recommends that the low bid from Stark Pavement Corp. in the amount of $1,246,755.36 be awarded. recommended for approvalPass Action details Video Video
ID#18-0576 1B. Bid/RFPBids Received: Friday, April 13, 2018, at 11:00 A.M. Westbound E. Moreland Bridge (B-67-248) Maintenance and Repairs The Board of Public Works recommends that the low bid from Fahrner Asphalt Sealers, LLC, in the amount of $64,692.77 be awarded.recommended for approvalPass Action details Video Video
ID#18-0577 1C. Bid/RFPBids Received: Friday, April 13, 2018, at 10:00 A.M. Main Street Reconstruction with Waukesha Water Utility The Board of Public Works concurs with the Waukesha Water Commission to award the low bid from Zignego Company Inc. in the amount of $3,282,725.40.recommended for approvalPass Action details Video Video
ID#18-0572 1A. Discussion and RecommendationReview and act on revised Change Order No. 3 with Absolute Construction Enterprises for Fire Station No. 3 and Police Substation project. recommended for Council ConsentPass Action details Video Video
ID#18-0579 1B. Discussion and RecommendationReview and act on the updated City of Waukesha Standard Construction Specifications - 2018 Edition, new Development Handbook, updated Construction Standard Details and new and updated Construction Administration Forms and authorize the Director of Public Works to amend these documents as necessary from time to time. recommended for Council ConsentPass Action details Video Video
ID#18-0590 1C. Discussion and RecommendationReview and act on Contract Change Order No. 1 with Musson Bros., Inc., for the River Valley Rd. Sanitary Sewer Extension and Fire Station No. 3 Access Rd. project. recommended for Council ConsentPass Action details Video Video
ID#18-0578 1A. Communications and ReferralsOfficial Notices: Bids to Close Friday, April 27, 2018, at 11:00 A.M. Area 5 Flood Mitigation Drop Off Center Parking Lot Paving 16,000LB Flatbed Trailer for Municipal Garage Two (2) New, Current Model Year, 5-6 Yard Dump Bodies with Plows, Wings and Sanders for Municipal Garage Two (2) New, Current Model Year, 12-17 Yard Dump Bodies with Plows, Wings and Sanders for Municipal Garage   Action details Not available
ID#18-0617 1B. Communications and Referrals2018 APWA Public Works Project of the Year Award.   Action details Video Video