ID#15-3854
| 1 | A. | | Minutes | Approve minutes from Dec. 3, 2015 | approved | Pass |
Action details
|
Video
|
|
ID#15-3857
| 1 | A. | | Discussion and Recommendation | Bids Received: Friday December 11, 2015 at 11:00am a. Summit Ave. & Delafield St. - Phase 2 Utility and Street Improvements.
The Board recommends that the low bid from State Contractors in the amount of $5,215,619.03 be recommended for approval | approved | Pass |
Action details
|
Video
|
|
ID#15-3859
| 1 | A. | | Discussion and Recommendation | Approve Contract Change Order No. 2 with Donohue & Associates, Inc. for the E. Moreland Blvd. Flood Mitigation Design | approved | Pass |
Action details
|
Video
|
|
ID#15-3861
| 1 | B. | | Discussion and Recommendation | Approve Storm Water Management Practice Maintenance Agreement between Kwik Trip, Inc and the City of Waukesha | held | |
Action details
|
Video
|
|
ID#15-3862
| 1 | C. | | Discussion and Recommendation | Approve Storm Water Management Practice Maintenance Agreement between HSA PrimeCare and the City of Waukesha | held | |
Action details
|
Video
|
|
ID#15-3863
| 1 | D. | | Discussion and Recommendation | Approve Storm Water Management Practice Maintenance Agreement between Metal Era, Inc and the City of Waukesha | held | |
Action details
|
Video
|