ID#15-2957
| 1 | A. | | Bid/RFP | Bids Received Wednesday July 8 2015 at 11:00 am.
a. E. Moreland Blvd. Flood Mitigation & Utility Improvements Manhattan Dr. to Wolf Rd. The BPW's recommends awarding contract to PTS Contractors on their low bid of $2,131,248. Recommendation is subject to approval of additional funding. | approved | Pass |
Action details
|
Video
|
ID#15-2955
| 1 | A. | | Discussion and Recommendation | Approve Contract Change Order No. 2 with Ray Stadler Construction Co., Inc. for the Les Paul Performance Center Remodel | recommended for Council Consent | Pass |
Action details
|
Video
|
ID#15-2990
| 1 | B. | | Discussion and Recommendation | Approve Engineering Consultant for Madison St. Structure Replacement Design Services | recommended for Council Consent | Pass |
Action details
|
Video
|
ID#15-2956
| 1 | A. | | Discussion and Authorization re: | To discuss and recommend to the "5 year Capitol Plan" that "Milky Way Road" be designed, engineered, and repaved to coincide with the development of a new City of Waukesha Park named Cardinal Ridge.
(Referral - Cummings) | | |
Action details
|
Video
|
ID#15-2958
| 1 | A. | | Communications and Referrals | Official Notice: Bids Close Friday, July 17, 2015 at 11:00 a.m.
a. 2015 Pavement Crackfilling
| recommended for approval | |