Public Works
Sponsors:
A motion was made by Ald. Joe Pieper, seconded by Member Kevin Reilly, that
the only bid from Hennes Services for the Cemetery Admin Building HVAC
Replacement project be recommended for approval. The motion carried by the
following vote:
3 - Steve Kassens, Kevin Reilly and Joe Pieper
2 - Chad O'Donnell and Eric E. Payne
Aye:
Absent:
C.
Bids Received: Friday, March 28, 2025, at 11:00 a.m.
Clean Water Plant Phase 3 Improvements
The Board of Public Works recommends that the low bid from J.F.Ahern
Co. in the amount of $18,600,000.00 be awarded.
Public Works
Sponsors:
A motion was made by Member Kevin Reilly, seconded by Ald. Joe Pieper, that
the low bid from J. F. Ahern Co. for the Clean Water Plant Phase 3 Improvements
project be recommended for approval. The motion carried by the following vote:
3 - Steve Kassens, Kevin Reilly and Joe Pieper
2 - Chad O'Donnell and Eric E. Payne
Aye:
Absent:
D.
Bids Received: Friday, March 28, 2025, at 11:00 a.m.
Prairie Home Cemetery Autumn Garden Fountain Improvements
The Board of Public Works recommends that the low bid from 4D
Exteriorscapes LLC in the amount of $45,000.00 be awarded.
Public Works
Sponsors:
A motion was made by Ald. Joe Pieper, seconded by Member Kevin Reilly, that
the only bid from 4D Exteriorscapes LLC for the Prairie Home Cemetery Autumn
Garden Fountain Improvements project be recommended for approval. The
motion carried by the following vote:
3 - Steve Kassens, Kevin Reilly and Joe Pieper
2 - Chad O'Donnell and Eric E. Payne
Aye:
Absent:
E.
Bids Received: Friday, March 28, 2025, at 11:00 a.m.
Gascoigne Drive and Peters Drive Utility and Street Improvements
The Board of Public Works recommends that the low bid from LaLonde
Contractors, Inc., in the amount of $3,246,364.78 be awarded.
Public Works
Sponsors: