A motion was made by Ald. Joe Pieper, seconded by Ald. Eric Payne, that the
Les Paul Performance Center Improvements bid be held. The motion carried by
the following vote:
5 - Kevin Reilly, Eric E. Payne, Joe Pieper, Steve Kassens and Chad O'Donnell
Aye:
B.
Bids Received: Friday, June 13, 2025, at 11:00 a.m.
Library HVAC Improvements
The Board of Public Works recommends only the base bid be awarded to
the low bidder, Lee Mechanical Inc., in the amount of $394,621.00.
Public Works
Sponsors:
A motion was made by Ald. Joe Pieper, seconded by Member Kevin Reilly, that
the low bid from Lee Mechanical, Inc., for the Library HVAC Improvements
project be recommended for approval. The motion carried by the following vote:
5 - Kevin Reilly, Eric E. Payne, Joe Pieper, Steve Kassens and Chad O'Donnell
Aye:
C.
Bids Received: Friday, June 13, 2025, at 11:00 a.m.
Horeb Springs Retaining Wall Improvements
The Board of Public Works recommends only the base bid be awarded to
the low bidder, All-Ways Contractors, Inc., in the amount of $488,906.00.
Public Works
Sponsors:
A motion was made by Ald. Joe Pieper, seconded by Member Kevin Reilly, that
the low bid from All-Ways Contractors, Inc., for the Horeb Springs Retaining Wall
Improvements be recommended for approval. The motion carried by the
following vote:
5 - Kevin Reilly, Eric E. Payne, Joe Pieper, Steve Kassens and Chad O'Donnell
Aye:
6. Matter of Report
City Engineer Brandon Schwenn reported that the CIP projects are in full swing.
7. Communications and Referrals:
A.
Official Notice: Bids to Close on Friday, June 27, 2025, at 11:00 a.m.
Minaka Park Resilient Surface Installation
Public Works
Sponsors:
Ald. Pieper asked that the project be bid with one color and multi-color for determining
the price difference.
8. Adjournment